Progress & Updates
Estimated Completion Date: Summer 2025
Land Cleared
Commenced October 1, 2024
Flooring Poured
Commenced December 18, 2024
Columns and Headers Added
Commenced January 13, 2025
Footing Poured
Commenced October 28, 2024
Block-work Commenced
Commenced December 23, 2024
Plunge Pools Excavated and Concrete Poured
Commenced January 20, 2025
Foundation Poured for Blue Fin Residents-Only Gym
Commenced January 24, 2025
Framing Completion
Commenced January 28, 2025






























Roof Trusses Installed




Commenced March 6, 2025
Ice and Water Shield Installation in Progress




Commenced March 21, 2025
Roof Shingles Installation in Progress
Commenced March 30, 2025




Drywall Installation in Progress




Commenced March 31, 2025
Roof Completed




Commenced April 3, 2025
Windows Installed



Commenced April 5, 2025
Interior Doors Installation in Progress




Commenced May 10, 2025
Exterior Columns in Progress




Commenced May 12, 2025